ANNEX 1  
  NAME OF AGENCY: ROAD SECTOR DEVELOPMENT TEAM (FEDERAL MINISTRY OF WORKS)  
         SUMMARY OF PROGRESS REPORT FOR THE PERIODIC MAINTENANCE CONTRACTS AS AT DECEMBER, 2013  
S/N Project Name State Orig. Leng (KM) Revised Leng (KM) Commencement Date: Completion Date Progress as at Time Elapsed %  
 
Original Revised Dec,  2013  
1 Jebba - Lafiagi Road NIGER STATE 23.04 22.04 5/23/2011 5/22/2012 7/22/2012 100% 100%  
2 Takai - Albasu - Gaya Road KANO STATE 34.70 34.70 5/2/2011 5/1/2012 9/1/2012 100% 100%  
3 Nafada - Gombeabba Road GOMBE STATE 9.70 10.15 5/23/2011 2/22/2012 - 100% 100%  
4 Hong - Mubi Road ADAMAWA STATE 48.00 17.50 5/2/2011 5/1/2012 8/1/2012 100% 100%  
5 Kurfi - Chiranchi Road KATSINA 26.50 22.00 5/23/2011 4/22/2012 - 100% 100%  
6 Okpala - Igwurita Road IMO STATE 18.20 24.00 8/1/2011 7/31/2012 2/28/2013 100% 100.00%  
7 Ado - Ilumoba - Agbado - Ikare Road Section A EKITI STATE 19.40 19.40 9/1/2011 5/31/2012 8/30/2012 100% 100%  
8 Dingaya - Galambi - Rungo Road JIGAWA STATE               18.50 16.70 9/1/2011 5/31/2012 3/5/2013 100% 100%  
9 Rumukurshi - Chokocho Road RIVERS STATE 16.50 9.10 9/1/2011 5/31/2012 8/30/2012 100% 100%  
10 Akure - Owo Road ONDO STATE               45.00 45.00 9/1/2011 8/31/2012 8/31/2013 100.00% 100.00%  
11 Ado - Ilumoba - Agbado - Ikare Road Section B EKITI STATE 30.60 30.60 2/1/2012 1/31/2013 8/31/2013 96.00% 95.83%  
12 Lafiagi - Mokwa Road NIGER STATE 23.00 11.50 2/1/2012 1/31/2013 - 100% 100.00%  
13 EastWest - Odi Road BAYELSA STATE 4.50 4.61 2/6/2012 11/5/2012 4/5/2013 100% 100.00%  
14 Lafia - Doma Road NASARAWA STATE 25.00 20.80 2/1/2012 1/31/2013 - 100% 100.00%  
                     

      

SUMMARY OF PROGRESS REPORT FOR THE REHABILITATION ROADS AS AT DECEMBER, 2013

 

 
S/N Project Name State Orig. Leng (KM) Revised Leng (KM) Commencement Date: Completion Date Progress as at Time Elapsed %  
 
Original Revised Dec,  2013  
1 Enugu - Abakaliki Road Enugu/Enbonyi 77.00 - 3/15/2012 3/16/2014 _ 67.50 89.58  
2 Ogoja Junction - Ikom Road Cross river 52.00 - 3/15/2012 3/16/2014 _ 80.00 89.58  
3 Mokwa - Bida Road Niger 121.00 _ 11/25/2013 10/24/2015 _ 0.00 0.00  
4 Akure - Ilesha Road Ondo/Osun 65.50 _ 11/25/2013 7/24/2015 _ 0.00 0.00  
5 Reconstruction of Abakaliki-Mbok (Ogoja Junction) Road Ebonyi/Cross River 86.00 85.90 16/11/2009 15/11/2011 15/6/2012 100 100  
6 Pavement Strengthening of Ikom-Mfum Road Cross River 25.00 22.60 16/11/2009 15/2/2011 15/7/2011 100 100  
                     
                     

 

ANNEX 3
                 
NAME OF AGENCY: ROAD SECTOR DEVELOPMENT TEAM (FEDERAL MINISTRY OF WORKS)
       SUMMARY OF PROGRESS REPORT ON PEDESTRIAN BRIDGES  CONTRACTS AS AT DECEMBER, 2013
               

 

 

S/No Project Name State Commencement Date Original Completion Dates Revised Completion Dates Progress Status (%) Elapsed Time (%) Remarks
FCT Pedestrian Bridges - Phase I
1 P/Bridge at Banex Jcn FCT 11/7/2012 1/10/2013 31/12/2013 85 100 Construction in progress; Construction delayed due to replacement of defective main beam
2 P/Bridge at NICON Jcn FCT 11/7/2012 1/10/2013 1/10/2013 99 100 Substantially completed as at November 2013; in defect liability period.
3 P/Bridge at Wuye Jcn FCT 11/7/2012 1/10/2013 31/12/2013 85 100 Construction in progress; Construction delayed due to replacement of defective main beam
4 P/Bridge at old Secretariat FCT 11/7/2012 1/10/2013 31/01/2014 95 100 Construction in progress; Construction delayed due to replacement of defective main beam
FCT Pedestrian Bridges - Phase II
5 P/Bridge at VIO/Mabushi FCT 17/09/2012 16/03/2013 31/12/2013 70 100 Construction in progress; Construction delayed due to redesign of extended span of main beam
6 P/Bridge at Sheraton Jcn FCT 17/09/2012 16/03/2013 31/01/2014 80 100 Construction in progress; Construction delayed due to redesign of extended span of main beam
Safety Measures
7 Road markings FCT 17/09/2012 16/03/2013 31/05/2013 100 100 Substantially completed as at May 2013; in defect liability period.
8 Install Traffic Signal FCT 17/09/2012 16/03/2013 31/05/2013 100 100 Substantially completed as at May 2013; in defect liability period.
9 Construction of Barricade Fencing FCT 17/09/2012 16/03/2013 31/05/2013 54 100

Construction in progress

 

 

 

ANNEX 3

NAME OF AGENCY: ROAD SECTOR DEVELOPMENT TEAM (FEDERAL MINISTRY OF WORKS)
       SUMMARY OF PROGRESS REPORT ON PROCUREMENT OF OPERATIONAL VEHICLES AND EQUIPMENTS FOR FEDERAL ROADS SAFETY CORPS (FRSC) AS AT DECEMBER, 2013
 

PHASE I - FRSC (GOODS) : SUPPORT TO FEDERAL ROADS SAFETY CORPS

 

Communication Equipment

 

1 4 Nos. VHF Base Station FCT   9/14/2012   100 100 No constraints; Completed
2 25 Nos. VHF Mobile Radio FCT   4/6/2012   100 100 No constraints; Completed
3 44 Nos. Walkie Talkies FCT   4/6/2012   100 100 No constraints; Completed

Operational Tools

 

4 1250 Nos. Breathalyzers FCT   4/6/2012   100 100 No constraints; Completed
5 17 Nos. Car Mounted Camera FCT   9/15/2012   100 100 No constraints; Completed
6 45 Nos. handheld Radar FCT   9/15/2012   100 100 No constraints; Completed
7 5 Nos. Digital & 5 Nos. Video cameras FCT   9/20/2011   100 100 No constraints; Completed

Vehicles and Equipment

 

8 16 Nos. Patrol Vehicles FCT    14/09/2012   100 100 No constraints; Completed
9 24 Nos. Patrol motorcycle FCT   9/14/2012 2/28/2013 90 100 No constraints; Completed
10 3 Nos. Heavy Tow Vehicles FCT   9/14/2012 4/16/2013 10 100 No constraints; Completed
11 1 No. Low Tow Vehicle FCT   9/14/2012 4/16/2013 10 100 No constraints; Completed
12 1 No. Single stretcher ambulance FCT   9/14/2012 2/28/2013 90 100 No constraints; Completed
13 6 Nos. Double stretcher ambulance FCT   9/14/2012 2/28/2013 100 100 No constraints; Completed

 

PHASE II - FRSC (GOODS) : SUPPORT TO FEDERAL ROADS SAFETY CORPS

Vehicles and Equipment

 

1 21 Nos. Patrol Vehicles FCT 21/11/2013 21/05/2014   100 100 No constraints; Completed
2 21 Nos. Patrol motorcycle FCT           Awaiting delivery
3 11 Nos. Single stretcher ambulance FCT           About to sign contract
4 3 Nos. Heavy Tow Vehicles FCT 18/11/2013 18/05/2013       Awaiting delivery

Operational Tools

 

5 45 Nos. Breathalyzers FCT       100 100 No constraints; Completed
6 21 Nos. Mounted cameras FCT 10/10/2013 10/2/2014       Awaiting delivery
7 40 Nos. Radar Guns FCT 12/9/2013 12/1/2014   100 100 No constraints; Completed
8 15 Nos. Digital Cameras FCT 13/09/2013 13/01/2014   100 100 No constraints; Completed
9 15 Nos. Video camera FCT 13/09/2013 13/01/2014   100 100 No constraints; Completed

Communication Equipment

 

10 10 Nos. VHF Base Station FCT 22/10/2013 22/02/2014       Awaiting delivery
11 30 Nos. VHF Mobile Radio FCT 22/10/2013 22/02/2014       Awaiting delivery
12 44 Nos. Walkie Talkies FCT 22/10/2013 22/02/2014      

Awaiting delivery

 

 

PHASE II - FRSC (CIVIL WORKS) : SUPPORT TO FEDERAL ROADS SAFETY CORPS

 

13 18 Nos. Ambulance Points FCT           Yet to commence

 

ANNEX 2

SUMMARY OF CONSULTANCY SERVICES 

 

             
S/No PROJECT      ORIGINAL  COMPLETION DATES REVISED  COMPLETION                  DATES   PROGRESS STATUS (%) ELAPSED TIME       REMARKS
1 Review & Update of Highway Manual 3/31/2013 8/31/2013 100% 100% Completed. No Constraints.
2 HDM4 Calibration 31/08/2013 12/31/2013 80% 100% The draft Final Report and Customized HDM-4 Workspace will be submitted by the consultant on or before Dec 31, 2013.
3 Project Monitoring & Evaluation 2/27/2014   35% 40% Project in progress
4 FRSC Capacity Building and Training Programme 12/19/2013 6/30/2014 30% 100% The programme was postponed by FRSC, the beneficiary establishment, to Jan 2014.
5 Implementation of Road Sector Governance and Accountability Action PLAN (GAAP) 1/31/2014  - 30% 60% Project in progress