The existing Highway Manual Part 1 – Design was revised in 2008 but the exercise was not finalized. The revision of the Part 2: Maintenance was concluded in 2009 but provisions were not made for Contract Maintenance Operations. Following the subject review in 2013, the new Nigeria Highway Manuals have now been published for immediate use by the Federal Ministry of Works, Highway Engineers and other stakeholders and available for free download on www.rsdt.gov.ng
This sub-component will support the development of an Asset Management System in the Ministry’s Department of Planning and Development. The system will be an integrated system for managing roads and bridge structures for use in the planning, programming and managing of works (capital, maintenance, rehabilitation and reconstruction) on roads and bridges on the Federal Road Network. This sub-component will finance consultancy services and equipment.
This sub-component will finance consultancy services for calibration and adaptation of HDM 4 model to Nigerian conditions. The project is currently ongoing and its final product will enhance the proper planning and allocation of funds for highway development and maintenance projects in Nigeria
Construction Equipment such as Truck Hoist & Flat Bed; Computers and Accessories; Welding Equipment & Tools; and Epoxy Resins have been fully procured and delivered to the Federal Roads Maintenance Agency (FERMA) for use on their bridges maintenance operations.
Pavement Evaluation Equipment such as Truck and a Four Wheel Drive (4WD); Laboratory Testing Equipment; and Computer & Accessories have been procured and delivered to the Federal Roads Maintenance Agency (FERMA) for use on their roads maintenance operations.
ANNEX 2 |
||||||
SUMMARY OF CONSULTANCY SERVICES |
||||||
S/No |
PROJECT |
ORIGINAL COMPLETION DATES |
REVISED COMPLETION DATES |
PROGRESS STATUS (%) |
ELAPSED TIME |
REMARKS |
1 |
Review & Update of Highway Manual |
3/31/2013 |
8/31/2013 |
100% |
100% |
Completed. No Constraints. |
2 |
HDM4 Calibration |
31/08/2013 |
12/31/2013 |
80% |
100% |
The draft Final Report and Customized HDM-4 Workspace will be submitted by the consultant on or before Dec 31, 2013. |
3 |
Project Monitoring & Evaluation |
2/27/2014 |
35% |
40% |
Project in progress |
|
4 |
FRSC Capacity Building and Training Programme |
12/19/2013 |
6/30/2014 |
30% |
100% |
The programme was postponed by FRSC, the beneficiary establishment, to Jan 2014. |
5 |
Implementation of Road Sector Governance and Accountability Action PLAN (GAAP) |
1/31/2014 |
- |
30% |
60% |
Project in progress |